Fundable Legacy Modernization Plans for Agency CIOs
Independent analysis by Starro. Not client work.

Objective
Why Legacy Modernization Plans Go Unfunded
GAO has found that many federal legacy systems lack a complete modernization plan, and funding boards that have seen savings slip now ask harder questions.
Our system is 30 years old, costs more each year and cannot be patched. What plan will a funding board approve, and will it still be true in year three?
Findings
An Eight-Section Plan Covering All 13 Requirements
The plan has eight sections. Sections 4, 5 and 7 answer GAO's three required elements: the work, the milestones and what happens to the old system. All 13 items, GAO's three elements and the fund's ten questions, map to at least one section.
Four rules make the plan fundable: draw the system first, tie each release of money to evidence, put a date on retiring the old system, and count cost savings and cost avoidance separately.

Approach
GAO Elements and TMF Questions Traced to Plan Sections
We read GAO's reports on legacy systems and on the Technology Modernization Fund, the fund's proposal template and its repayment guidance. Then we built a plan structure from the method we use on hardware programs: requirements first, a drawing of the system before anyone builds, reviews at set points, and test evidence before hand-off.

Validation
Coverage Checked Against GAO and TMF Sources
How we checked the plan:
All three GAO plan elements and all ten TMF proposal questions mapped to plan sections.
Milestone structure checked against the fund's rules for stepped funding and repayment.
Sources checked against GAO-25-107795, GAO-26-107737 and the TMF guidance by an independent reviewer.
The spend curve is an illustrative shape, not agency data.
Recommendations
Release Funds Only Against Milestone Evidence
A plan built this way answers a funding board's questions before they are asked. It stays true in year three because every milestone is a check the board can make. Check the fund's current status before you apply.
Tools used:
Current and target architecture drawings; phased migration plan; GAO plan-element checklist